| Leach Field Design and Installation
notes A leachate field will be installed in the
Southern corner of Cell 2 to supply known quantities of
liquid to the area over the pressure transducers. An
aerial view of the leach field installation is shown in
Figure 1. The leachate field will be fed via four
individual pipes spaced as shown in Figure 2. Each pipe
will be 200 feet in length with a perforated section of
120 feet. The end of the perforated section will be
capped. The field will be placed approximately 8 feet
above the surface of the leachate collection system as
shown in Figure 3. This placement will ensure the pipes
clear the contractors berm and allow the fabricator
to cut off excess pipe and weld on a threaded fitting.
The leach field will be installed using the following
steps:
- A University of Central Florida team member will
mark pipe installation locations along the
Southern boundary of Cell 2 as shown in Figure 1.
Assuming the waste will be filled from west to
east, pipes will be installed one at a time at
these marked locations when waste elevations of 8
feet are reached. The pipes will be pre-assembled
down the slope of the contractors berm and
will be ready for installation at that stage.
- The pipes will be installed by dragging a pipe
section into the waste mass such that it runs
roughly parallel to the LCS laterals. The
perforated (capped) end of the pipe will be in
the waste mass and approximately 5 feet of the
solid pipe will protrude out over the
contractors berm at the location of the
marker.
- Ideally, University of Florida will be notified
at the time of placement and they will survey the
pipe location. If this is not possible, the
landfill operator will note the vertical
elevation of the waste and pipe at the marked
locations.
- One of the transducers located in the gray and
green box will be installed adjacent to the pipe.
The pipe installation marker will have the code
for the appropriate transducer marked on it.
Slack will be left in the cable to allow for
settling and shifting.
- Waste filling will continue until the waste
elevation at the next marker reaches 8 feet.
Steps 2 through 4 will then be repeated for the
installation of this pipe.
- This sequence of filling and installing will be
repeated until all of the pipes have been
installed.
- The University of Central Florida team will be
notified once all the pipes have been installed.
- The pipe fabricator will be contacted to
co-ordinate completion of the following tasks:
- Cut off all of the pipes approximately at the
contractors berm,
- Weld a threaded fitting onto the end of each
pipe.
It is important to note that clay should be avoided as
daily cover in the waste mass between the LCS and the
leachate field. The inclusion of clay will impair this
experiment and complicate data analysis. It is most
desirable that an alternative material be used in the 8
feet of waste over the transducers and in the first 5
feet of waste over the perforated pipe section.
|